Road Name | Detour Plan | Scheduled Closure Dates | Estimated Duration |
Description | Expected Public Hearing Date |
County Line Road at Elm Creek | 12/04/2023 thru 9/18/2024 | 9 months | The proposed work is cross culvert replacements on County Line Road at Elm Creek | ||
Springdale Road | Springdale Road Sidewalk Detour Plan | 11/04/2024 thru 11/08/2024 | 1 week | The road closure is to allow crane operations to complete the pedestrian bridge installation. | 10/22/2024 |